Technical brochure
TB 878 WG A1.48

Guidance on high-speed testing of turbo generator rotors

Engineers responsible for generator maintenance are often posed with the difficult question of whether to send the rotor off-site for high-speed balancing and testing or not. It is generally considered that by doing so is the lower risk option, however there can be substantial operational and financial pressures against doing so. This guide aims to provide operators with information required to help them make informed decisions as to whether to carry out high speed testing of generator rotors following repair or maintenance. The practice varies substantially across the world and engineers can be presented with difficult decisions to make under financial pressure.

Members

Convenor (UK)

B. ADAMS

B. FENTON (US), B. MARCUSO (US), N. SMIT (NZ), B. O’SULLIVAN (EI), G. CSABA (SE), J. PORTER (UK), G. YAN (CN), H. SHIMADA (JP), B. MOORE (US), S. MITCHELL (UK), V. FERNABUT (FR), K. MIYAIKE (JP)

During the manufacture of high-speed turbine generators, the rotors undergo a number of tests to prove their integrity, both mechanically and electrically, from standstill to running speed and overspeed as well as from ‘cold’ to operating temperature, to ensure that the rotor does not exhibit high vibrations which may limit its operation in service. The following tests are typically carried out to prove that:

  • The components of the rotor have the mechanical integrity to operate within the full speed range expected in normal operation
  • The vibration levels of the rotor are acceptable through its run up, at rated speed and overspeed.
  • The rotor is thermally stable, i.e., the vibration levels stay within acceptable levels as the rotor heats up, and, that the thermal stability is repeatable.
  • The integrity of the insulation is maintained throughout the speed range, i.e., there are no rotor ground faults, and no inter-turn insulation defects.

These tests are carried out at the factory to prove the equipment is within requirements and limit the risk of operational issues at the plant. The worst-case scenario is that a severe mechanical defect would cause destruction of the rotor at site, causing catastrophic damage. This is a very rare occurrence in modern times, more likely is that a problem may occur at site which causes high vibrations, either requiring the generator rotor to be returned to a facility for correction, or for operational limits to be imposed. This work is usually referred to simply as “balancing” and there are relatively few facilities around the world capable of such work on large turbogenerators.

Testing is expensive and may add months to an outage program. It is common for engineers to face pressure to reduce outage timescales and cost, and to consider whether high speed testing of the rotor is necessary. Furthermore, the rotor is a costly strategic spare part, and the operator will want to have it ready to be used on site as required. A working group was set up in order to explore these issues to help users of generators make a better, informed decision as to whether they should opt to carry out high speed testing or not.

Scope and Methodology

The Working Group investigated the following:

  • The scope of work which would require high-speed testing
  • The availability of high-speed testing facilities
  • Any guidance already in existence on this subject
  • OEM guidance.
  • 3rd party service provider’s guidance.
  • The risk of introducing issues following work
  • The risk remaining if high speed testing is not carried out
  • Ways in which the risk could be mitigated.

The Working Group produced a questionnaire. Operators, OEMs, independent testing organisations and consultants were invited to share their experiences with generator rotor issues, what tests they would normally specify, and what problems they had experienced. The collected information was assessed and used to create a guide. However, it should be noted that the majority of responses came from European operators where it is an accepted practice to carry out high speed testing.

A risk matrix was created showing work carried out and relative risk if high speed testing is omitted from the work scope.

Description of the TB

The Technical Brochure provides detailed information on how generator rotors are constructed to assist the reader with understanding how and where various issues may develop.

Generator Rotors

The rotor is the rotating component which is coupled (directly or indirectly) to the prime mover. The rotor is a high-speed component which carries DC current through coils wound into machined forged steel shaft. Slots are cut into the steel, within which strips of copper are inserted. These strips of copper are connected in series to form a large coil of many turns, which are insulated from each other (Figure 1 and 2).  Applied current creates a magnetic field, which when spun by the turbine provides the excitation to the main armature coils within the generator stator to produce the output. Most conventional rotors for high output generators are 2-pole and will operate at the system frequency (3000 or 3600rpm) with some, notably most generators installed in nuclear plants, operating at half speed (1500 or 1800rpm), and can weigh up to several hundred tonnes. 

Figure 1 - Generator rotor endwinding with retaining ring

Figure 2 - Rotor coil removed from the forging removed

Potential issues and repairs

Potential issues with the rotor are addressed in chapter 3 from an electrical and mechanical point of view and examples are shown. Finally, the topic of...

To read this article subscribe to ELECTRA. Single edition, annual options and CIGRE membership are available. Access to all editions is free for CIGRE members.

Already have an account? Sign in

Subscribe now

A1

Power generation and electromechanical energy conversion

This Technical Brochure has been created by a Working Group from the CIGRE Power generation and electromechanical energy conversion Study Committee which is one of CIGRE's 16 domains of work.
The SC covers all aspects of electromechanical energy conversion equipment, rotating electrical machines for power generation, grid support, and energy conversion within industrial applications. This includes research, development, design, manufacture and testing of power generation and electromechanical energy conversion equipment and their associated auxiliaries, commissioning, operation, condition assessment, maintenance, life extension, refurbishment, upgrades, efficiency improvement, conversion, storage and de-commissioning.

Learn more
Top of page